IMM also examines the rail system construction site, which was done and stopped in the past, with its main lines. Work has started on the Mahmutbey-Esenyurt Metro, which is the continuation of the Mecidiyeköy-Mahmutbey Metro. It is aimed for a service for the future 3 staff of the city.
Istanbul Metropolitan Municipality (BB), IMM Rail System Department Head Pelin Alpkökin, who gave information about the work on the Mahmutbey-Esenyurt Metro, which was built and operated in 2017 and was never started, on 2 August, is on duty in 2019 of the Mahmutbey-Esenyurt Metro. that he was one of the hats they took over while standing in their duties

KABATAŞ-ESENYURT WILL BE CONNECTED

Stating that the Mahmutbey-Esenyurt Metro is this very important project that appeals to the city’s side, Alpkökin said, “This line, which is the continuation of the Mecidiyeköy-Mahmutbey Metro, is the metro Mecidiyeköyamamçunuğı kadeviköy? . When we complete all these projects, we will have the opportunity to travel as intense and safe as a train from Kabataş to Istanbul.”

STARTING AUGUST 2

With the issuance of Eurobonds at the end of last year, they allocated a budget of 220 million Euros for the Mahmutbey-Esenyurt Metro, and they have been working on the project somewhat since then:

“Unfortunately, the line that was tendered in the past is used for redesigning, first of all, to design and optimize projects in order to project in viable and detail. At the same time, there were problems with the delivery of excavations to the contractor for us, which was very important to us. they will not be resolved. Now we are solving all these problems. We will see the production of Mahmutbey-Esenyurt Metro on August 2.”

IN THE FIRST STAGE, 7 KM WILL BE DONE

Alpkökin, in the first place, will start 7 km from Mahmutbey-Kanuni Sultan Süleyman Hospital of the line, which they took over from the previous administration as never before, my memories 20 Then we will continue our metro until Esenyurt. It is a project used in the design of the subway used in the city.

WHICH LINES WILL IT BE INTEGRATED?

. At Mahmutbey Station; M3 Kirazlı-Basaksehir-Olimpiyatkoy Metro

. At Mehmet Akif Station; Atakoy-Ikitelli Metro

. At Temapark Station; Halkalı – Arnavutköy – 3. Airport Metro